Tuesday, August 13, 2013

Welcome to Muscat

The staff has started to arrive here in Muscat for their first day at the school on Thursday, August 15th. As you can see it is another wonderful day here with highs around 34C.

Saturday, August 10, 2013

Thursday, August 8, 2013

Kindergarten Classroom

The first of the Kindergarten classrooms is close to being completed with the flooring installed now.

Monday, August 5, 2013

Resources from Alberta

The school central storage room is starting to fill with resources from Alberta. The good people at United Library Services has been fantastic to work with in filling the needs for the school. The resources, textbooks, and library books exceeded $500,000 and ULS was able to handle all parts of a challenging & culturally distinct order.

Sunday, August 4, 2013

Vinyl Flooring

The air conditioning is now functioning in the school building so the flooring in the non-tile areas can commence. The tiling has already been installed & here the vinyl flooring is being adhered.

Saturday, August 3, 2013

Covering Support

The steel structure to support the cover for the playground & football pitch continues to be put into place in preparation for the cover installation.

Thursday, August 1, 2013

School at Night

The permanent power connection is now completed so here is a view of the school at night during testing of the lights.